Transportation of equipment from Combwich Wharf northbound along the C182 to the Hinkley Point C construction site.
Due to the size and shape of this equipment, these deliveries will be managed via an escorted ‘rolling roadblock’ and will likely cause delays along this route on these dates. We apologise in advance for any inconvenience this may cause.
Although this isn’t a full closure of the road, you may like to use an alternative route between the hours of 9am-5pm to avoid a delay on the below date:
Sunday 29th January 2023
If you do encounter part of the roadblock, please do follow the instructions of the escort team who will assist with the safe management of traffic.
If you have also signed up to our text messaging service, you will receive further confirmation via text 2-3 days before.
If you wish to find out further details please email: edfenergy@hpcenquiries.com or call us on 0333 009 7070.
We thank you in advance for your patience and support whilst we move some of the most critical pieces of equipment and infrastructure that will enable us to complete construction of the new Nuclear Power station.